Select Page

Ministry of Public Works and Public Housing (PUPR) be responsible for preparing the infrastructure to support the 2018 upcoming Asian Games in Jakarta and Palembang.

Until now the completion of the construction and rehabilitation of the venue as well as regional arrangements Bung Karno and Pensions Athletes in Kemayoran continues to speed up. Minister PUPR, Basuki Hadimuljono optimistic venues rehabilitation project at the Bung Karno (GBK) Senayan and Kemayoran Wisma development athletes will be completed on time in October 2017 later.

Based on data from the Asian Games Task Force XVIII Infrastructure Ministry of Public Works and Public Housing (PUPR), as of November 17 2016, the physical work of rehabilitation of the swimming stadium has reached 10,26% of the plan 10,21%.

Rehabilitation Istora Bung Karno (GBK) has reached its physical work progress 5,16 4,66%% of the plan, the construction of the realization exercise facility 0,64 0,34%% of the plan.

While the largest construction job in the rehabilitation field Main Stadium GBK today progress has reached 4,32% of the target 4,57%.

Rehabilitation Field Hockey, Archery, Football A / B / C realizations have reached 22% of the plan 24,8%. While the Center Court Indoor Tennis and realization 11,01% of the target 15,65%.

As for the arrangement of GBK region, the physical work will be done at the beginning 2017. Structuring GBK region do to create quality outdoor space building a better venue but can be integrated with the building.

Improvements were also made to the exterior of the building infrastructure such as gates, counters, pedestrian, parking, fencing, seating, toilet. Then the marker area, food court, playground, outdoor gym and garbage.

Meanwhile the realization of the construction of the realization of Wisma Atlet Kemayoran Blok C-2 28,9% and the realization of Block D-10 has reached 32,7% of the 31,6% plan.

The topping off plan for the tower that has 18 and 24 floors will be done at the end of 2016, and for 32 floor towers in January or February 2017.

The athlete's house will have 10 tower. Three tower blocks of flats built on an area C2 27.654 1.932 square meters with a capacity of residential units and seven towers in Block D10 on an area of ​​square meters with 79.400 5.494 dwelling unit

Source: okezone.com